Plan of the Day: June 24 (Monday)
Following roads will be closed and reopened at the end of the day:
700E (from 2400N to 2500N) C-284
600E (from 2150N to 3rd st) pre-pulverization
2500N (from 700E to 800E) aggregate capping
2750N (from CH5 to 900E) seal coat
Followings roads will be partially closed and reopened at the end of the day:
900E (from 2600N to 2750N) dirt shoulders
Following roads will be closed and reopened on 06/30/24:
2150N (from CH5 to 600E) soil cement stabilization
700E (from 2400N to 2500N) soil cement cure