Plan of the Day: July 1 (Monday)
The following roads will be closed and reopened at the end of the day:
775E (from 2050N to 2150N) C-42
2150N (from 700E to 775E) pre-pulverization
700E (from 2150N to IL RT10) pre-pulverization
The following roads will be partially closed and reopened at the end of the day:
2700N (from 700E to 800E) dirt shoulders
800E (from 2500N to 2750N) dirt shoulders
The following roads will be closed and reopened on 07/05/24:
800E (from IL RT10 to 2400N) soil cement sure
The following roads will be closed and reopened on 07/07/24:
800E (from 2150N to IL RT10) soil cement stabilization