Plan Of The Day: June 18
The following will be closed and reopened at end of day June 18 2024
2150N (from CH 5 to 675E) Culvert 245B
800E (from 2500N to 2600N) Pre-pulverization. Residents will have access to the north
2750N (700E to 900E) Aggregate Capping. Residents will have access to the east
700E (from 2900N to 30370N) Dirt Shoulders. Residents will have access to the north
3070N (from 700E to 800E) Dirt Shoulders. Residents will have access to east
2750N (from CH 5 to 800E) Dirt Shoulders. Residents will have access to the east
800 E (from 2500N to 2750N) Soil Cement Cure. Residents will have access to the north
The following will be closed 6/18/2024 and reopened 6/23/2024
2500N (from 800E to 900E) Soil Cement Stabilization