Plan Of The Day: April 24
The following road will be closed and reopened on 4/26/2024
900 E (from 2750 N to I-74) Cement Stabilization
The following roads will be closed and reopened by end of day 4/24/2024
1100 E (from 3200 N to 3300 N) Culvert C-84
1100 E (from 3300 N to 3400 N) Culvert C-238
3200 N (from 900 E to CH 2) Roadway Prep
900 E (from US 150 to 3300 N) Roadway Prep
In addition, the following work is planned for Thursday 4/25 and Friday 4/26;
Thursday 4/25
Culvert Installation
C-235 (700 E between 2750 N and 2900 N)
C-51 (700 E between 2750 N and 2900 N)
Cement Stabilization
900 E between 2750 N and US 150
Roadway Prep
3200 N between 900 E and CH 2
900 E between US 150 and 3300 N
Friday 4/26
Culvert Installation
C-51 (700 E between 2750 N and 2900 N)
Cement Stabilization
900 E between 2750 N and US 150
4" Aggregate Cap
900 E between US 150 and 3300 N
Roadway Prep
3200 N between 900 E and CH2
Anticipated work may be altered due to weather, equipment breakdowns or any other unforeseen circumstances.