Plan of the Day: June 11

Following roads will be closed and reopened at the end of the day: 2700N (from 700E to 800E) pre-pulverization CH5 (from IL RT10 to County Line) aggregate shoulders 2750N (from CH2 to 700E) aggregate capping 3200N (from 900E to CH2) dirt shoulders Following roads will be closed and reopened on 06/16/24: 2750N (from 700E to 1000E) soil cement cure Following roads will be closed and reopened on 06/17/24: 2750N (from 800E to 900E) soil cement stabilization