Plan of the Day: June 11
Following roads will be closed and reopened at the end of the day:
2700N (from 700E to 800E) pre-pulverization
CH5 (from IL RT10 to County Line) aggregate shoulders
2750N (from CH2 to 700E) aggregate capping
3200N (from 900E to CH2) dirt shoulders
Following roads will be closed and reopened on 06/16/24:
2750N (from 700E to 1000E) soil cement cure
Following roads will be closed and reopened on 06/17/24:
2750N (from 800E to 900E) soil cement stabilization
