The following road will be closed and reopened at the end of the day:
- 1100E (From 3300N to 3400N) Culvert work C-201
In addition, the following work is anticipated for Monday 04/08/2024 and Tuesday 04/09/2024:
Monday 04/08/2024:
- Culvert Installation: C-45 (Riprap) 800 E between IL Rt 10 and 2400 N
C-255 800 E between 2150 N and 2200 N
C-230 3200 N between 1000 E and 1100 E
- Roadway Prep.: 2500 N between 400 E and CH 5
2600 N between 400 E and CH 5
900 E between 2750 N and US 150
Tuesday 04/09/2024:
- Culvert Installation: C-256 800 E between 2150 N and 2200 N
C-257 700 E between 2150 N and IL Rt 10
C-230 (Riprap) 3200 N between 1000 E and 1100 E
- Roadway Prep.: CH 5 between IL Rt 10 and 2750 N
2500 N between 400 E and CH 5
2600 N between 400 E and CH 5
900 E between 2750 N and US 150
Anticipated work may be affected by weather, equipment breakdown or any other unforeseen circumstance.