PLAN OF THE DAY: APRIL 06

The following road will be closed and reopened at the end of the day:

  • 1100E (From 3300N to 3400N) Culvert work C-201

 

In addition, the following work is anticipated for Monday 04/08/2024 and Tuesday 04/09/2024:


Monday 04/08/2024: 

  • Culvert Installation:  C-45 (Riprap)  800 E between IL Rt 10 and 2400 N
                                   C-255             800 E between 2150 N and 2200 N
                                   C-230             3200 N between 1000 E and 1100 E

 

  • Roadway Prep.:         2500 N between 400 E and CH 5
                                    2600 N between 400 E and CH 5
                                    900 E between 2750 N and US 150

 

Tuesday 04/09/2024: 

  • Culvert Installation:  C-256   800 E between 2150 N and 2200 N
                                   C-257   700 E between 2150 N and IL Rt 10
                                   C-230 (Riprap)  3200 N between 1000 E and 1100 E

 

  • Roadway Prep.:        CH 5 between IL Rt 10 and 2750 N
                                   2500 N between 400 E and CH 5
                                   2600 N between 400 E and CH 5
                                   900 E between 2750 N and US 150

    Anticipated work may be affected by weather, equipment breakdown or any other unforeseen circumstance.