Following roads will be closed and reopened at the end of the day:
- 800E (from IL RT10 to 2400N) culvert work C-45(riprap)
- 800E (from 2150N to 2200N) culvert work C-255
- 3200N (from 1000E to 1100E) culvert work C-230
- 2500N (from 400E to CH5)
- 2600N (from 400E to CH5)
- 700/725E (from 2900N to 3070N)
- 3070N (from 725E to 800E)
Following roads will be closed and reopened on 04/12/24:
- 900E (from 2750N to US150)
In addition, the following work is anticipated for Tuesday 04/09/2024:
Tuesday 04/09/2024: Culvert Installation:
- C-256 800 E between 2150 N and 2200 N
- C-257 700 E between 2150 N and IL Rt 10
- C-230 (Riprap) 3200 N between 1000 E and 1100 E
Roadway Prep.:
- CH 5 between IL Rt 10 and 2750 N
- 2500 N between 400 E and CH 5
- 2600 N between 400 E and CH 5
900 E between 2750 N and US 150
Anticipated work may be affected by weather, equipment breakdown or any other unforeseen circumstance.