Plan of the Day: April 10

Following roads will be closed and reopened at the end of the day:

  • CH5 (from IL RT10 to 2750N)
  • 3070N (from 725E to 800E)
  • 700/725E (from 2900N to 3070N)
  • 900E (from US150 to 3200N)
  • 800E (from 2200N to IL RT10) culvert work C-273
  • 2150N (from 600E to 700E) culvert work C-274
  • 1200E (from 3300N to 3400N) culvert work C-266
  • 1200E (from 3200N to 3300N) culvert work C-267

The following work is anticipated for Thursday 04/11/2024 and Friday 04/12/2024:

Thursday 04/11/2024:  Culvert Installation:

  • C-271  700 E between 2400 N and 2500 N
  • C-272  800 E between IL Rt 10 and 2400 N

Roadway Prep.: 

  • 700/725 E between 2900 N and 3070 N
  • 900 E between US 150 and 3200 N

Friday 04/12/2024:   Culvert Installation:

  • C-254 800 E between 2500 N and 2600 N
  • C-268 900 E 2600 N and 2750 N

C-155 900 E between 2900 N and US 150

Roadway Prep.: 

  • 700/725 E between 2900 N and 3070 N
  • 900 E between US 150 and 3200 N


Anticipated work can be altered by weather, equipment breakdown, or any other unforeseen circumstances.