Following roads will be closed and reopened at the end of the day:
- CH5 (from IL RT10 to 2750N)
- 3070N (from 725E to 800E)
- 700/725E (from 2900N to 3070N)
- 900E (from US150 to 3200N)
- 800E (from 2200N to IL RT10) culvert work C-273
- 2150N (from 600E to 700E) culvert work C-274
- 1200E (from 3300N to 3400N) culvert work C-266
- 1200E (from 3200N to 3300N) culvert work C-267
The following work is anticipated for Thursday 04/11/2024 and Friday 04/12/2024:
Thursday 04/11/2024: Culvert Installation:
- C-271 700 E between 2400 N and 2500 N
- C-272 800 E between IL Rt 10 and 2400 N
Roadway Prep.:
- 700/725 E between 2900 N and 3070 N
- 900 E between US 150 and 3200 N
Friday 04/12/2024: Culvert Installation:
- C-254 800 E between 2500 N and 2600 N
- C-268 900 E 2600 N and 2750 N
C-155 900 E between 2900 N and US 150
Roadway Prep.:
- 700/725 E between 2900 N and 3070 N
- 900 E between US 150 and 3200 N
Anticipated work can be altered by weather, equipment breakdown, or any other unforeseen circumstances.