Plan of the Day: April 13

Following roads will be closed and reopened at the end of the day:

  • 1200E (from 3200N to 3300N) culvert work C-267
  • 900E (from US150 to 3300N)
  • 3300N (from 1400E to 1500E)
  • 1500E (from 3200N to 3300N)
  • 3200N (from 1100E to 1200E)

Following roads will be closed and reopened on 04/19/24:

  • 900E (from 2750N to US150) culvert work C-155

In addition, the following work is anticipated for Monday 04/15/2024 and Tuesday 04/16/2024:

Monday 04/15/2024:  Culvert Installation:

  • C-254     800 E between 2500 N and 2600 N 
  • C-270    2400 N between 400 E and CH 5
  • C-155       900 E between 2750 N and US 150

Roadway Prep.:     

  • 900 E between 2750 N and 3300 N

Tuesday 04/16/2024:  Culvert Installation:

  • C-269 & C-258    2500 N between 400 E and CH 5
  • C-155             900 E between 2750 N and US 150

Roadway Prep and Cement Stabilization:   900 E between 2750 N and 3300 N

Anticipated work can be altered by weather, equipment breakdown, or any other unforeseen circumstances.