Plan Of The Day: April 17

Due to high wind conditions, no cement stabilization will be occurring today 4/17/2024 on 900E between 3200N and I-74.  The road remains closed for cement cure.   

 

The following roads will be closed on 4/17/2024 and reopened by end of day:

  • 3200N (From 900E to CH 2) Roadway preparation
  • 1200E (From 3200N to 3300N) Roadway preparation
  • 900E (From 2750N to US 150) Culvert work C-155
  • 2500E (From 400E to CH 5) Culvert work C-269 & C-258

The following will be closed on 4/17/2024 and remain closed until 4/24/2024

  • 900E (From 2750N to 3300N) Cement Stabilization

In addition, the following work is anticipated for Thursday 04/17/2024 and Friday 04/18/2024:

Thursday 04/17/2024: 

Culvert Installation:

C-230  3200 N between 1000 E and 1100 E

C-259 2500 N between 400 E and CH 5
C-263  2600 N between 400 E and CH 5

Cement Stabilization:       

900 E between 2750 N and 3300 N

                                       Roadway Prep.:             1400 E between 3100 N and 3300 N

Friday 04/18/2024;        Culvert Installation:    C-230 (Riprap) 3200 N between 1000 E and 1100 E
                                                                         C-268 900 E between 2600 N and 2750 N 
                                                                          C-39 Entrance culvert 900 E between 2600 N and 2750 N        


                                    Cement Stabilization:    900 E between 2750 N and 3300 N

                                    Roadway Prep.:             3200 N between 900 E and CH 2