Plan of the Day: April 22_

Following roads will be closed and reopened at the end of the day:

  • 3200N (from 900E to 1200E) 
  • 3200N (from 1000E to 1100E) culvert work C-230 riprap
  • 1100E (from 3200N to 3300N) culvert work C-84
  • 700E (from 2900N to 3070N) culvert work C-280
  • 800E (from 2300N to 2400N) culvert work C-45A

Following roads will be closed for cement stabilization and reopened on 04/25/24:

  • 900E (from US150 to I74)
  • 900E (from 2750N to US150)

 

The following work is anticipated for Tuesday 4/23/2024

  • Culvert Installation: C-221 on 700 E between 2750 N and 2900 N
  •  Roadway Prep: 3200 N between 1100 E and CH 2
  • Cement Stabilization:  900 E between 2750 N and US 150

Anticipated work may be altered by weather conditions, equipment breakdowns, or any other unforeseen circumstance.