Plan Of The Day: April 24

The following road will be closed and reopened on 4/26/2024

  • 900 E (from 2750 N to I-74) Cement Stabilization

The following roads will be closed and reopened by end of day 4/24/2024

  • 1100 E (from 3200 N to 3300 N) Culvert C-84
  • 1100 E (from 3300 N to 3400 N) Culvert C-238
  • 3200 N (from 900 E to CH 2) Roadway Prep
  • 900 E (from US 150 to 3300 N) Roadway Prep

In addition, the following work is planned for Thursday 4/25 and Friday 4/26;

Thursday 4/25

Culvert Installation

  • C-235 (700 E between 2750 N and 2900 N)
  • C-51 (700 E between 2750 N and 2900 N)

Cement Stabilization

  • 900 E between 2750 N and US 150 

Roadway Prep

  • 3200 N between 900 E and CH 2 
  • 900 E between US 150 and 3300 N 

 

Friday 4/26

Culvert Installation 

  • C-51 (700 E between 2750 N and 2900 N)

Cement Stabilization

  • 900 E between 2750 N and US 150

4" Aggregate Cap

  • 900 E between US 150 and 3300 N 

Roadway Prep

  • 3200 N between 900 E and CH2

 

Anticipated work may be altered due to weather, equipment breakdowns or any other unforeseen circumstances.