The following roads will be closed and reopened as noted below:
- 900 E (US-150 to 3300 N) 4" Cap 4/30/2024
- 700 E (2750 N to 3070 N) Box Culverts end of day 4/27/2024
The following roads will be closed and reopened on 04/29/24 for soil cement cure:
- 900E (from 2750N to US150)
In addition, the following work is anticipated for Monday 04/29/2024 and Tuesday 04/30/2024:
Monday 04/29/2024: Aggregate Cap/Shoulders 900 E between 2750 N and 3300 N
Shoulders 1100 E between 3200 N and 3300 N
Shoulders 1200 E between 3200 N and 3300 N
Shoulders 3200 N between 900 E and CH 2
Culvert Installation 700 E between 2750 N and 3070 N (C-225)
Cement Stabilization 1500 E between 3200 N and 3300 N
Tuesday 04/30/2024: Aggregate Cap/Shoulders 900 E between 2750 N and 3300 N
Culvert Installation 700 E between 2750 N and 3070 N (C-224)
Cement Stabilization 3300 N between 1400 E and 1500 E
Anticipated work can be altered by weather, equipment breakdowns, or any other unforeseen circumstance.