Plan of the Day: April 27

The following roads will be closed and reopened as noted below:

  • 900 E (US-150 to 3300 N) 4" Cap 4/30/2024
  • 700 E (2750 N to 3070 N) Box Culverts end of day 4/27/2024

The following roads will be closed and reopened on 04/29/24 for soil cement cure:

  • 900E (from 2750N to US150) 

In addition, the following work is anticipated for Monday 04/29/2024 and Tuesday 04/30/2024:

Monday 04/29/2024:   Aggregate Cap/Shoulders  900 E between 2750 N and 3300 N
                                    Shoulders                          1100 E between 3200 N and 3300 N
                                    Shoulders                          1200 E between 3200 N and 3300 N
                                    Shoulders                           3200 N between 900 E and CH 2
                                    Culvert Installation              700 E between 2750 N and 3070 N (C-225)
                                    Cement Stabilization         1500 E between 3200 N and 3300 N

Tuesday 04/30/2024:  Aggregate Cap/Shoulders    900 E between 2750 N and 3300 N
                                    Culvert Installation               700 E between 2750 N and 3070 N (C-224)
                                    Cement Stabilization          3300 N between 1400 E and 1500 E

Anticipated work can be altered by weather, equipment breakdowns, or any other unforeseen circumstance.