The following roads will be closed and reopened at the end of the day:
- 700E (from 2900N to 3070N) C-234 extension
- 2400N (from 400E to CH5) aggregate capping
In addition, the following is anticipated for Tuesday 08/06/24:
Tuesday 08/06/24: Culvert Installation CH 10 between 1000E and 1100E (C-32)
4" Aggregate Cap 2400N between 400E and CH 5
Anticipated work may be altered by inclement weather, equipment,breakdowns, or any other unforeseen circumstances.