The following roads will be partially closed and reopened at the end of the day:
- 2400N (from 400E to 700E) dirt shoulders
- 2500N (from 400E to CH5) dirt shoulders
In addition, the following work is anticipated for Thursday 08/15/24 and Friday 08/16/24:
Thursday 08/15/24: Dust Control Seal Coat: 2400N between 400E and CH 5
2500N between 400E and CH 5
2600N between County Line and CH 5
Dirt Shoulders: 775 E between 2050N and 2150N
600E between 2150N and 3rd St.
Friday 08/16/24: Culvert Extensions: Intersection of 2500N and 700E
Dirt Shoulders 2500N between County Line and CH 5
2600N between 400E and CH 5
Seeding 800E 2150N and 2400N
2150N between CH 5 and 800E
Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.