The following roads will be closed and reopened at the end of the day:
- CH10 (from 1100E to 1200E) C-29
In addition, the following work is anticipated for Monday 08/26/24 and Tuesday 08/27/24:
Monday 08/26/24: Culvert Extension 2500N between 800E and 900E (C-111)
Permanent Seeding Goose Creek Township
Tuesday 08/27/24: Culvert Extension 2750N between 800E and 900E (C-52)
Permanent Seeding Goose Creek Township
Anticipated work may be altered by inclement weather, equipment breakdown, or any other unforeseen circumstances.