Plan of the Day: July 1 (Monday)

The following roads will be closed and reopened at the end of the day:

  • 775E (from 2050N to 2150N) C-42
  • 2150N (from 700E to 775E) pre-pulverization
  • 700E (from 2150N to IL RT10) pre-pulverization

The following roads will be partially closed and reopened at the end of the day:

  • 2700N (from 700E to 800E) dirt shoulders
  • 800E (from 2500N to 2750N) dirt shoulders

The following roads will be closed and reopened on 07/05/24:

  • 800E (from IL RT10 to 2400N) soil cement sure

The following roads will be closed and reopened on 07/07/24:

  • 800E (from 2150N to IL RT10) soil cement stabilization

 

 

 

In addition, the following work is anticipated for Tuesday 07/02/2024:

07/02/2024:  Culvert Installation    2150N between CH 5 and 600E (C-244B)
                     Cement Stabilization 775 E between 2050N and 2150N
                     Pre Pulverization       770 E between 2150N and 2300N
                                                       2400N between CH 5 and 700E
                      4" Aggregate Cap     2150N between 600E and 800E 

Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.