The following roads will be closed and reopened at the end of the day:
- 775E (from 2050N to 2150N) C-42
- 2150N (from 700E to 775E) pre-pulverization
- 700E (from 2150N to IL RT10) pre-pulverization
The following roads will be partially closed and reopened at the end of the day:
- 2700N (from 700E to 800E) dirt shoulders
- 800E (from 2500N to 2750N) dirt shoulders
The following roads will be closed and reopened on 07/05/24:
- 800E (from IL RT10 to 2400N) soil cement sure
The following roads will be closed and reopened on 07/07/24:
- 800E (from 2150N to IL RT10) soil cement stabilization
In addition, the following work is anticipated for Tuesday 07/02/2024:
07/02/2024: Culvert Installation 2150N between CH 5 and 600E (C-244B)
Cement Stabilization 775 E between 2050N and 2150N
Pre Pulverization 770 E between 2150N and 2300N
2400N between CH 5 and 700E
4" Aggregate Cap 2150N between 600E and 800E
Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.