Plan Of The Day: July 03 (Wednesday)

The following will be closed and reopened end of day 07/03/2024

  • 2150 N (from CH 5 to 600E)  Culvert C-244B
  • 2400N (from CH 5 to 700E) Pre Pulverization 
  • 2400N (from CH 5 to 400E) Pre Pulverization
  • 2500N (from 700E to 900E) Partial closure for work on dirt shoulders, residents can access to the east
  • 700E (from 2400N to 2500N) Partial closure for work on dirt shoulders

The following will be closed and remain closed through 07/09/2024

  • 775E (from 2050N to 2150N)   Soil Cement Stabilization  (No affected residents on this road segment) 
  • 2150N (from 700E to 775E) Soil Cement Stabilization (No affected residents on this road segment) 
  • 800E (from 2150N to IL Rt 10) Soil Cement Cure.  Residents can access from the north 

In addition, there will be no work on public roadways on Thursday 07/04/24 and Friday 07/05/2024. Work will resume Monday 7/8/2024.