The following will be closed and reopened end of day 07/03/2024
- 2150 N (from CH 5 to 600E) Culvert C-244B
- 2400N (from CH 5 to 700E) Pre Pulverization
- 2400N (from CH 5 to 400E) Pre Pulverization
- 2500N (from 700E to 900E) Partial closure for work on dirt shoulders, residents can access to the east
- 700E (from 2400N to 2500N) Partial closure for work on dirt shoulders
The following will be closed and remain closed through 07/09/2024
- 775E (from 2050N to 2150N) Soil Cement Stabilization (No affected residents on this road segment)
- 2150N (from 700E to 775E) Soil Cement Stabilization (No affected residents on this road segment)
- 800E (from 2150N to IL Rt 10) Soil Cement Cure. Residents can access from the north
In addition, there will be no work on public roadways on Thursday 07/04/24 and Friday 07/05/2024. Work will resume Monday 7/8/2024.