Plan of the Day: July 10 (Wednesday)

The following roads will be closed and reopened at the end of the day:

  • 2150N (from CH5 to 600E) C-244B
  • 2150N (from 700E to 775E) soil cement cure (road closed to thru traffic)
  • 775E (from 2050N to 2150N) soil cement cure (road closed to thru traffic)

The following roads will be partially closed and reopened at the end of the day:

  • 800E (from IL RT10 to 2400N) dirt shoulders

The following roads will be closed and reopened on 07/12/14:

  • 2400N (from CH5 to 700E) roadway preparation

The followings roads will be closed and reopened on 07/17/24:

  • 700E (from 2150N to IL RT10) soil cement stabilization

In addition, the following work is anticipated for Thursday 07/11/24 and Friday 07/12/24:

Thursday 07/11/24:  Culvert Installation        2150N between CH 5 and 600E (C-249)
                                 Cement Stabilization     700E between IL Rt 10 and 2400N
                                 4" Aggregate Cap          775E between 2050N and 2150N
                                 Dirt Shoulder                 800E between IL Rt 10 and 2400N

Friday 07/12/24        Culvert Installation        700E between 2150N and IL Rt 10
                                 Cement Stabilization     2400N between CH 5 and 700E
                                4" Aggregate Cap           800E between 2150N and IL Rt 10
                                Dirt Shoulder                  800E between IL Rt 10 and 2400N
 
Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.