The following roads will be closed and reopened at the end of the day:
- 2150N (from CH5 to 600E) C-244B
- 2150N (from 700E to 775E) soil cement cure (road closed to thru traffic)
- 775E (from 2050N to 2150N) soil cement cure (road closed to thru traffic)
The following roads will be partially closed and reopened at the end of the day:
- 800E (from IL RT10 to 2400N) dirt shoulders
The following roads will be closed and reopened on 07/12/14:
- 2400N (from CH5 to 700E) roadway preparation
The followings roads will be closed and reopened on 07/17/24:
- 700E (from 2150N to IL RT10) soil cement stabilization
In addition, the following work is anticipated for Thursday 07/11/24 and Friday 07/12/24:
Thursday 07/11/24: Culvert Installation 2150N between CH 5 and 600E (C-249)
Cement Stabilization 700E between IL Rt 10 and 2400N
4" Aggregate Cap 775E between 2050N and 2150N
Dirt Shoulder 800E between IL Rt 10 and 2400N
Friday 07/12/24 Culvert Installation 700E between 2150N and IL Rt 10
Cement Stabilization 2400N between CH 5 and 700E
4" Aggregate Cap 800E between 2150N and IL Rt 10
Dirt Shoulder 800E between IL Rt 10 and 2400N
Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.