Plan of the Day: July 11 (Thursday)

The following roads will be closed and reopened at the end of the day:

  • 2150N (from CH5 to 600E) C-249
  • 2400N (from CH5 to 600) roadway preparation
  • 700E (from 2150N to 2400N) roadway preparation
  • 775E (from 2050N to 2150N) aggregate capping
  • 2150N (from 700E to 775E) aggregage capping

The following roads will be partially closed and reopened at the end of the day:

  • 800E (from IL RT10 to 2400N) dirt shoulders

In addition, the following work is anticipated for Friday 07/12/24:

Friday 07/12/24        Culvert Installation        700E between 2150N and IL Rt 10
                                 Cement Stabilization     2400N between CH 5 and 700E
                                4" Aggregate Cap           800E between 2150N and IL Rt 10
                                Dirt Shoulder                  800E between IL Rt 10 and 2400N
 
Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen