Plan of the Day: July 13 (Saturday)

The following roads will be closed and reopened at the end of the day:

  • 700E (from 2150N to IL RT10) C-107
  • 2150N (from 600E to 700E) aggregate capping

The following roads will be closed and reopened on 07/15/24:

  • 2400N (from CH5 to 700E) roadway preparation
  • 700E (from IL RT10 to 2400N) roadway preparation

 

In addition, the following work is anticipated for Monday 07/15/24 and Tuesday 07/16/24:

Monday 07/15/24     Culvert Installation      700E between 2150N and IL Rt 10 (C-107) cleanup
                                 Cement Stabilization   700E between 2150N and IL Rt 10
                                 4" Aggregate Cap       2150N between 700E and 800E
                                                                       800E between 2150N and IL Rt 10

Tuesday 07/16/24    Culvert Installation      3200N between 900E and 1000E (C-283)
                                 Cement Stabilization   700E between 2150N and IL Rt 10
                                                                     700E between IL Rt 10 and 2400N
                                 4" Aggregate Cap        800E between 2150N and IL Rt 10

 
Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.