The following roads will be closed and reopened at the end of the day:
- 700E (from 2150N to IL RT10) C-107
- 2150N (from 600E to 700E) aggregate capping
The following roads will be closed and reopened on 07/15/24:
- 2400N (from CH5 to 700E) roadway preparation
- 700E (from IL RT10 to 2400N) roadway preparation
In addition, the following work is anticipated for Monday 07/15/24 and Tuesday 07/16/24:
Monday 07/15/24 Culvert Installation 700E between 2150N and IL Rt 10 (C-107) cleanup
Cement Stabilization 700E between 2150N and IL Rt 10
4" Aggregate Cap 2150N between 700E and 800E
800E between 2150N and IL Rt 10
Tuesday 07/16/24 Culvert Installation 3200N between 900E and 1000E (C-283)
Cement Stabilization 700E between 2150N and IL Rt 10
700E between IL Rt 10 and 2400N
4" Aggregate Cap 800E between 2150N and IL Rt 10
Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.