Plan of the Day: July 15 (Monday)

The following roads will be closed and reopened at the end of the day:

  • 2150N (from 700E to 800E) aggregate capping
  • 800E (from 2150N to IL RT10)

The following roads will be closed and reopened on 07/22/24:

  • 700E (from 2150N to IL RT10) soil cement stabilization
  • 700E (from IL RT10 to 2400N) roadway preparation
  • 2400N (from CH5 to 700E) roadway preparation

In addition, the following work is anticipated for Tuesday 07/16/24:


Tuesday 07/16/24    Culvert Installation      3200N between 900E and 1000E (C-283)
                                 Cement Stabilization   700E between 2150N and IL Rt 10
                                                                     700E between IL Rt 10 and 2400N
                                 4" Aggregate Cap        800E between 2150N and IL Rt 10

 
Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.