The following roads will be closed and reopened at the end of the day:
- 700E (from 2150N to IL RT10) soil cement stabilization
- 700E (from IL RT10 to 2400) soil cement stabilization
- 800E (from 2150N to IL RT10) aggregate capping
In addition, the following work is anticipated for Thursday 07/18/24 and Friday 07/19/24:
Thursday 07/18/24 Culvert installation (C-283) 3200N between 900E and 1000E
Rip Rap C-107 700E between 2150n and IL RT 10
Cement Stabilization 700E between IL RT 10 and 2400N
Cement Stabilization 2400N between CH5 and 700E
Dirt shoulders 800E between IL RT 10 and 2400
Friday 07/19/24 Culvert installation (C-283) clean up 3200N between 900E and 1000E
Cement Stabilization 700E between IL RT 10 and 2400N
Cement Stabilization 2400N between CH5 and 700E
Dirt shoulders 800E between IL RT 10 and 2400
Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.