Plan of the Day: July 17 (Wednesday)

The following roads will be closed and reopened at the end of the day:

  • 700E (from 2150N to IL RT10) soil cement stabilization
  • 700E (from IL RT10 to 2400) soil cement stabilization
  • 800E (from 2150N to IL RT10) aggregate capping

In addition, the following work is anticipated for Thursday 07/18/24 and Friday 07/19/24:

 

Thursday 07/18/24    Culvert installation (C-283)   3200N between 900E and 1000E

                                             Rip Rap C-107   700E between 2150n and IL RT 10

                                             Cement Stabilization   700E between IL RT 10 and 2400N

                                             Cement Stabilization  2400N between CH5 and 700E

                                             Dirt shoulders  800E between IL RT 10 and 2400

 

Friday 07/19/24    Culvert installation (C-283) clean up  3200N between 900E and 1000E

                                             Cement Stabilization   700E between IL RT 10 and 2400N

                                             Cement Stabilization  2400N between CH5 and 700E

                                             Dirt shoulders  800E between IL RT 10 and 2400

 

Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.