The following roads will be closed and reopened at the end of the day:
- 700E (from 2150N to IL RT10) aggregate capping
- 2400N (from CH5 to 700E) soil cement cure
The following roads will be closed and reopened on 07/29/24:
- 2600N (from County Line to CH5)
The following roads will be closed and reopened on 07/30/24:
- 2500N (from 400E to CH5) soil cement stabilization
In addition, the following the work is anticipated for Monday 07/22/24 and Tuesday 07/23/24:
Monday 07/22/24 Field Tile Repair 700E between 2150N and IL Rt 10 (C-106)
Cement Stabilization 2400N between 400E and CH 5
4" Aggregate Cap 700E between IL Rt 10 and 2400N
Tuesday 07/23/24 Culvert Installation CH 10 between 900E and 1000E (C-34B)
Cement Stabilization 2500N between 400E and CH 5
4" Aggregate Cap 700E between 2150N and IL Rt 10
Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstance.