Plan of the Day: July 24 (Wednesday)

The following roads will be closed and reopened at the end of the day:

  • 2400N (from CH5 to 700E) aggregate capping

The following roads will be closed and reopened on 07/29/24:

  • 2600N (from County Line to CH5) soil cement cure
  • 2500N (from 400E to CH5) soil cement cure

The following roads will be closed and reopened on 07/30/24:

  • 2400N (from 400E to CH5) soil cement stabilization

In addition, the following work is anticipated for Thursday 07/25/24 and Friday 07/26/2024:

Thursday 07/25/24:    Culvert Installation              CH 10 between 900E and 1000E (C-34B)
                                   Cement Stabilization          2400N between 400E and CH 5
                                   4" Aggregate Cap               2400N between CH 5 and 700E

Friday 07/26/24:        Culvert Installation              CH 10 between 900E and 1000E (C-34B)  Cleanup
                                  Dust Control (Seal Coat)    700E between 2150N and 2400N
                                                                             2400N between CH 5 and 700E

Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.