The following roads will be closed and reopened at the end of the day:
- 2400N (from CH5 to 700E) aggregate capping
The following roads will be closed and reopened on 07/29/24:
- 2600N (from County Line to CH5) soil cement cure
- 2500N (from 400E to CH5) soil cement cure
The following roads will be closed and reopened on 07/30/24:
- 2400N (from 400E to CH5) soil cement stabilization
In addition, the following work is anticipated for Thursday 07/25/24 and Friday 07/26/2024:
Thursday 07/25/24: Culvert Installation CH 10 between 900E and 1000E (C-34B)
Cement Stabilization 2400N between 400E and CH 5
4" Aggregate Cap 2400N between CH 5 and 700E
Friday 07/26/24: Culvert Installation CH 10 between 900E and 1000E (C-34B) Cleanup
Dust Control (Seal Coat) 700E between 2150N and 2400N
2400N between CH 5 and 700E
Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.