The following roads will be closed and reopened at the end of the day:
- CH10 (from 900E to 1000E) C-34B
- 2400N (from CH5 to 700E) aggregate capping
The following roads will be closed and reopened on 07/30/24:
- 2400N (from 400E to CH5) soil cement stabilization
In addition, the following work is anticipated for Friday 07/26/2024:
Friday 07/26/24: Culvert Installation CH 10 between 900E and 1000E (C-34B) Cleanup
Dust Control (Seal Coat) 700E between 2150N and 2400N
2400N between CH 5 and 700E
Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.