Plan of the Day: July 27 (Saturday)

The following roads will be closed and reopened on 07/30/24:

  • 2400N (from 400E to CH5) soil cement cure

There will be no work on public roads on Saturday 07/27/24.  In addition, the following work is anticipated for Monday 07/29/24 and Tuesday 07/30/24:

Monday 07/29/24:      Off load culverts along CH 10
                                   4" Aggregate Cap   2500N between 400E and CH 5

Tuesday 07/30/24:      General cleanup at various culvert locations
                                    4" Aggregate Cap  2400N between 400E and CH 5

Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.