The following roads will be closed and reopened by end of day 7/8/2024
- 2500N (from 400E to CH 5) Pre-Pulverization
- 2500N (from County Line to CH 5) Pre-Pulverization
- 800E (from IL Rt 10 to 2400N) Aggregate Capping
- 2500N (from 700E to 900E) Partial closure- Dirt Shoulders. Residents will have access to West
- 700E (from 2400N to 2500N) Partial Closure- Dirt Shoulders
- 800 E (from 2150N to IL Rt. 10) Soil Cement Cure. Residents will have access to South
The following roads will be closed and reopened end of day 7/9/2024
- 775E (from 2050N to 2150N) Soil Cement Cure
The following road will be closed and reopened end of day 7/15/2024
- 2150N (from 700E to 775E) Soil Cement Stabilization
In addition, the following work is planned for Tuesday 7/9/2024
Tuesday 07/09/24: Culvert Installation 2150N between CH 5 and 600E (C-244B)
Cement Stabilization 700E between IL Rt 10 and 2400N
Pre Pulverization 2600N between County Line and CH 5
Aggregate Cap 800E between 2150N and IL Rt 10
Dirt Shoulder 700E between 2400N and 2500N