Following roads will be closed and reopened at the end of the day:
- 775E (from 2050N to 2150N) C-41
In addition, the following work is anticipated for Monday 06/03/2024 and Tuesday 06/04/2024:
Monday 06/03/2024: Culvert Installation: 2150 N between 775E and 800E (C-43)
Cement Stabilization: 2750N between CH 5 and 700E
3200N between 1000E and 1100E
Add Rock: 2700N between 700E and 800E
Dirt Shoulder: 2750N between 600E and 1000E
4" Aggregate Cap: 700E between 2750N and US 3070N
3070N between 700E and 800E
HMA Binder: CH 5 between IL Rt 10 and County Line
Tuesday 06/04/2024: Culvert Installation: 800E between 2600N and 2700N (C-50)
Cement Stabilization: 2750N between 700E and 800E
HMA Binder: CH 5 between IL Rt 10 and County Line
Dirt Shoulder: 2700N between 700E and 800E
4" Aggregate Cap: 700E between 2750N and 2900N