Following roads will be closed and reopened at the end of the day:
- 775E (from 2050N to 2150N) C-41 riprap
- 2150N (from 775E to 800E) C-43
- 2700N (from 700E to 800E) add rock
- 2750N (from 600E to 1000E) dirt shoulder
- 3070N (from 700E to 800E) aggregate capping
- 3200N (from 1000E to 1100E) add rock
- CH5 (from IL RT10 to County Line) HMA binder
Following roads will be closed and reopened on 06/05/24
- 700E (from 2750N to 2900E) soil cement cure
Following roads will be closed and reopened on 06/06/24
- 900E (from 2600E to 2750N) soil cement cure
Following roads will be closed and reopened on 06/07/24
- 2750N (from CH5 to 600E) soil cement cure
Following roads will be closed and reopened on 06/10/24
- 2750N (from CH5 to 700E) soil cement stabilization
In addition, the following work is anticipated for Tuesday 06/04/2024:
Tuesday 06/04/2024: Culvert Installation: 800E between 2600N and 2700N (C-50)
Cement Stabilization: 2750N between 700E and 800E
HMA Binder: CH 5 between IL Rt 10 and County Line
Dirt Shoulder: 2700N between 700E and 800E
4" Aggregate Cap: 700E between 2750N and 2900N