Plan of the Day: June 03

Following roads will be closed and reopened at the end of the day:

  • 775E (from 2050N to 2150N) C-41 riprap
  • 2150N (from 775E to 800E) C-43
  • 2700N (from 700E to 800E) add rock
  • 2750N (from 600E to 1000E) dirt shoulder
  • 3070N (from 700E to 800E) aggregate capping
  • 3200N (from 1000E to 1100E) add rock
  • CH5 (from IL RT10 to County Line) HMA binder

Following roads will be closed and reopened on 06/05/24

  • 700E (from 2750N to 2900E) soil cement cure

Following roads will be closed and reopened on 06/06/24

  • 900E (from 2600E to 2750N) soil cement cure

Following roads will be closed and reopened on 06/07/24

  • 2750N (from CH5 to 600E) soil cement cure

Following roads will be closed and reopened on 06/10/24

  • 2750N (from CH5 to 700E) soil cement stabilization

 

In addition, the following work is anticipated for  Tuesday 06/04/2024:

Tuesday 06/04/2024:  Culvert Installation:       800E between 2600N and 2700N (C-50)
                                    Cement Stabilization:   2750N between 700E and 800E
                                    HMA Binder:                   CH 5 between IL Rt 10 and County Line    

                                    Dirt Shoulder:               2700N between 700E and 800E
                                   4" Aggregate Cap:          700E between 2750N and 2900N