Plan of the Day: June 05

Following roads will be closed and reopened at the end of the day:

  • 2150N (from 775E to 800E) C-43
  • CH5 (from IL RT10 to County Line) HMA binder
  • 3200N (from 900E to CH2) dirt shoulders
  • 1100E (from 3200N to 3300N) dirt shoulders
  • 1200E (from 900E to CH2) dirt shoulders

Following roads will be closed and reopend on 06/11/24:

  • 2750N (from 600E to 700E) soil cement stabiliztion
  • 2750N (from CH5 to 700E) soil cement cure
  • 3200N (from 1000E to 1100E) soil cement cure

In addition, the following work is anticipated for Thursday 06/06/24 and Friday 06/07/24:

Thursday 06/06/24:  Culvert Installation        2150N between 775E and 800E (C-43 Riprap)
                                 Cement Stabilization     2750N between 700E and 800E
                                 HMA Binder                   CH 5 between IL Rt 10 and County Line
                                 Dirt Shoulder                 1200E between 3200N and 3400N
                                                                       1100E between 3200N and 3300N
                                                                       3200N between 900E and CH 2
|
Friday 06/07/24:      Culvert Installation         800E between 2600N and 2700N
                                Cement Stabilization      2750N between 800E and 900E
                                HMA Binder                    CH 5 between IL Rt 10 and County Line
                                Dirt Shoulder                  1200E between 3200N and 3300N
                                                                       1100E between 3200N and 3300N
                                                                       3200N between 900E and CH 2

Anticipated work may be altered due to weather conditions, equipment breakdown, or any other unforeseen circumstance.