Following roads will be closed and reopened at the end of the day:
- 2150N (from 775E to 800E) C-43
- CH5 (from IL RT10 to County Line) HMA binder
- 3200N (from 900E to CH2) dirt shoulders
- 1100E (from 3200N to 3300N) dirt shoulders
- 1200E (from 900E to CH2) dirt shoulders
Following roads will be closed and reopend on 06/11/24:
- 2750N (from 600E to 700E) soil cement stabiliztion
- 2750N (from CH5 to 700E) soil cement cure
- 3200N (from 1000E to 1100E) soil cement cure
In addition, the following work is anticipated for Thursday 06/06/24 and Friday 06/07/24:
Thursday 06/06/24: Culvert Installation 2150N between 775E and 800E (C-43 Riprap)
Cement Stabilization 2750N between 700E and 800E
HMA Binder CH 5 between IL Rt 10 and County Line
Dirt Shoulder 1200E between 3200N and 3400N
1100E between 3200N and 3300N
3200N between 900E and CH 2
|
Friday 06/07/24: Culvert Installation 800E between 2600N and 2700N
Cement Stabilization 2750N between 800E and 900E
HMA Binder CH 5 between IL Rt 10 and County Line
Dirt Shoulder 1200E between 3200N and 3300N
1100E between 3200N and 3300N
3200N between 900E and CH 2
Anticipated work may be altered due to weather conditions, equipment breakdown, or any other unforeseen circumstance.