Plan of the Day: June 08

Following roads will be closed and reopened at the end of the day:

  • CH5 (from IL RT10 to County Line) HMA binder
  • 900E (from 2600N to 2750N) aggregate capping
  • 700E (from 2700N to 2750N) aggregate capping
  • 3070N (from 700E to 800E) seal coat
  • 700E (from 2750N to 3070N) seal coat
  • 3200N (from 1000E to 1100E) seal coat

Following roads will be closed and reopened on 06/10/24

  • 800E (from 2600N to 2750N) C-50 overnight closure

Following roads will be closed and reopened on 06/12/24:

  • 2750N (from 700E to 1000E) soil cement cure 

In addition, the following work is anticipated for Monday 06/10/24 and Tuesday 06/11/24:

Monday 06/10/24:   Culvert Installation        800E between 2600N and 2700N (C-50)
                                Cement Stabilization   2750N between 900E and 1000E
                                HMA Binder                 CH 5 between IL Rt 10 and County Line
                                Dirt Shoulders            1200E between 3200N and 3300N
                                                                   1100E between 3200N and 3300N
                                                                   3200N between 900E and CH 2

Tuesday 06/11/24: Culvert Installation       2150N between 600E and 700E (C-220)
                              Cement Stabilization    2750N between 800E and 900E
                              Aggregate Shoulders     CH 5 between IL Rt 10 and County Line
                              Dirt Shoulders              1200E between 3200N and 3300N
                                                                   1100E between 3200N and 3300N
                                                                   3200N between 900E and CH 2

Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.