Following roads will be closed and reopened at the end of the day:
- CH5 (from IL RT10 to County Line) HMA binder
- 900E (from 2600N to 2750N) aggregate capping
- 700E (from 2700N to 2750N) aggregate capping
- 3070N (from 700E to 800E) seal coat
- 700E (from 2750N to 3070N) seal coat
- 3200N (from 1000E to 1100E) seal coat
Following roads will be closed and reopened on 06/10/24
- 800E (from 2600N to 2750N) C-50 overnight closure
Following roads will be closed and reopened on 06/12/24:
- 2750N (from 700E to 1000E) soil cement cure
In addition, the following work is anticipated for Monday 06/10/24 and Tuesday 06/11/24:
Monday 06/10/24: Culvert Installation 800E between 2600N and 2700N (C-50)
Cement Stabilization 2750N between 900E and 1000E
HMA Binder CH 5 between IL Rt 10 and County Line
Dirt Shoulders 1200E between 3200N and 3300N
1100E between 3200N and 3300N
3200N between 900E and CH 2
Tuesday 06/11/24: Culvert Installation 2150N between 600E and 700E (C-220)
Cement Stabilization 2750N between 800E and 900E
Aggregate Shoulders CH 5 between IL Rt 10 and County Line
Dirt Shoulders 1200E between 3200N and 3300N
1100E between 3200N and 3300N
3200N between 900E and CH 2
Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.