The following roads will be closed and reopened at the end of the day:
- 800E (from 2600N to 2700N) C-50
- 2750N (from 800E to 900E) soil cement stabilization
- 800E (from 2600N to 2750N) pre-pulverization
- CH5 (from IL RT10 to County line) HMA binder
- 3200N (from 900E to CH2) dirt shoulders
- 700E (from 2700N to 2750N) aggregate capping
- 2750N (CH2 to 700E) aggregate capping
The following roads will be closed and reopened on 06/12/24
- 2750N (from 700E to 800E) soil cement cure
In addition, the following work is anticipated for Tuesday 06/11/24:
Tuesday 06/11/24: Culvert Installation 2150N between 600E and 700E (C-220)
Cement Stabilization 2750N between 800E and 900E
Aggregate Shoulders CH 5 between IL Rt 10 and County Line
Dirt Shoulders 1200E between 3200N and 3300N
1100E between 3200N and 3300N
3200N between 900E and CH 2
Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.