Plan of the Day: June 10

The following roads will be closed and reopened at the end of the day:

  • 800E (from 2600N to 2700N) C-50
  • 2750N (from 800E to 900E) soil cement stabilization
  • 800E (from 2600N to 2750N) pre-pulverization
  • CH5 (from IL RT10 to County line) HMA binder
  • 3200N (from 900E to CH2) dirt shoulders
  • 700E (from 2700N to 2750N) aggregate capping
  • 2750N (CH2 to 700E) aggregate capping

The following roads will be closed and reopened on 06/12/24

  • 2750N (from 700E to 800E) soil cement cure

In addition, the following work is anticipated for Tuesday 06/11/24:

Tuesday 06/11/24: Culvert Installation       2150N between 600E and 700E (C-220)
                              Cement Stabilization    2750N between 800E and 900E
                              Aggregate Shoulders     CH 5 between IL Rt 10 and County Line
                              Dirt Shoulders              1200E between 3200N and 3300N
                                                                   1100E between 3200N and 3300N
                                                                   3200N between 900E and CH 2

Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.