Following roads will be closed and reopened at the end of the day:
- 2700N (from 700E to 800E) pre-pulverization
- CH5 (from IL RT10 to County Line) aggregate shoulders
- 2750N (from CH2 to 700E) aggregate capping
- 3200N (from 900E to CH2) dirt shoulders
Following roads will be closed and reopened on 06/16/24:
- 2750N (from 700E to 1000E) soil cement cure
Following roads will be closed and reopened on 06/17/24:
- 2750N (from 800E to 900E) soil cement stabilization