The following roads will be closed and reopened at the end of the day:

  • 2150N (from 600E to 700E) C-220
  • 2700N (from 700E to 800E) soil cement stabilization
  • 800E (from 2600N to 2750N) pre-pulverization
  • 2750N (from 600E to 800E) aggregate capping
  • CH5 (from IL RT10 to County Line) aggregate shoulders
  • 3200N (from 900E to 1200E) dirt shoulders
  • 700E (from 2750N to 3070N) dirt shoulders
  • 3070N (from 700E to 800E) dirt shoulders

The following roads will be closed and reopened on 06/15/24:

  • 2750N (from 800E to 1000E) soil cement cure

In addition, the following work is anticipated for Thursday 06/13/24 and Friday 06/14/24:

Thursday 06/13/24:  Culvert Installation        3200N between 900E and 1000E (C-228 extension)
                                 Cement Stabilization      800E between 2600N and 2750N
                                 Pre Pulverization            800E between 2500N and 2600N
                                 Aggregate Shoulders     CH 5 between IL Rt 10 and County Line
                                 4" Aggregate Cap          2750N between 700E and 800E
                                 Dirt Shoulders                3070N between 700E and 800E
                                                                        700E between 2750N and 3070N

Friday 06/14/24:     Culvert Installation           800E between 2600N and 2700N (C-50 Riprap)
                               Cement Stabilization       800E between 2500N and 2600N
                               Pre Pulverization            2500E between 800E and 900E   
                               4" Aggregate Cap           2750N between 700E and 800E
                               Dirt Shoulders                700E between 2750N and 3070N
                                                                      3070N between 700E and 800E