Following roads will be closed and reopened at the end of the day:
- 3200N (from 900E to 1000E) C-228
- 800E (from 2600N to 2750N) soil cement stabilization
- 2750N (from 700E to 800E aggregate capping
- CH5 (from IL RT10 to County Line) HMA shoulders
- 3070N (from 700E to 800E) dirt shoulders
- 700E (from 2750N to 3070N) dirt shoulder
Following roads will be closed and reopened on 06/15/24:
- 2750N (from 800E to 1000E) soil cement cure
Following roads will be closed and reopened on 06/19/24:
- 2700N (from 700E to 800E) soil cement cure
Following roads will be closed and reopened on 06/21/24:
- 800E (from 2600N to 2750N) soil cement stabilization
In addition, the following work is anticipated for Friday 06/14/24:
Friday 06/14/24: Culvert Installation 800E between 2600N and 2700N (C-50 Riprap)
Cement Stabilization 800E between 2500N and 2600N
Pre Pulverization 2500E between 800E and 900E
4" Aggregate Cap 2750N between 700E and 800E
Dirt Shoulders 700E between 2750N and 3070N
3070N between 700E and 800E
Anticipated work may be altered due to weather conditions, equipment breakdowns, or any other unforeseen circumstances.