Plan Of The Day: June 14

The following will be closed and reopened end of day 6/14/2024

  • 3070N (from 700E to 800E) Dirt Shoulders- Partial closure, residents will have access to the east
  • 700E (from 2700N to 3070N) Dirt Shoulders- Partial closure, residents will have access to the north
  • 2750N (from 700E to 800E) Aggregate Capping -Partial closure, residents will have access to the east
  • 2500N (from 700E to 900E) Pre Pulverization- Full closure, residents will have access to the west
  • 2500N (from 800E to 900E) Culvert 285 replacement

The following will be closed and reopened end of day 6/17/2024

  • 900E (2850N to US 150) Culvert replacement
  • 2700N (700E to 800E) Soil Cement Cure

The following will be closed and reopened end of day 6/18/2024

  • 800E (from 2600N to 2750N) Soil Cement Cure- residents will have access to the north

The following will be closed and reopened end of day 06/21/2024

  • 800E (from 2500N to 2600N) Soil Cement Stabilization- residents will have access to the south