Plan of the Day: June 15

The following roads will be closed and reopened on 06/15/24:

  • 2750N (from CH5 to 800E) seal coat
  • 700E (from 2700N to 2750N) seal coat
  • 900E (from 2600N to 2750N) seal coat

The following roads will be closed and reopened on 06/16/24:

  • 2700N (from 700E to 800E) soil cement cure

The following roads will be closed and reopened on 06/21/24:

  • 800E (from 2500N to 2750N) soil cement cure

In addition, the following work is anticipated for Monday 06/17/24 and Tuesday 06/18/24:

Monday 06/17/24:     Culvert Installation:      2150N between CH 5 and 675E (C-245A)
                                  Cement Stabilization: 2500N between 800E and 900E
                                  Pre Pulverization:       2500N between 700E and 800E
                                  Paint Pavt Mkr.:          CH 5 between IL Rt 10 and County Line
                                 4" Aggregate Cap:      2750N between 700E and 1000E
                                 Dirt Shoulders:           3070N between 700E and 800E
                                                                     700E between 2700N and 3070N

Tuesday 06/18/24:    Culvert Installation:   2150N between CH 5 and 675E (C-245B)
                                 Cement Stabilization: 2500N between 700E and 800E
                                 Pre Pulverization:        700E between 2400N and 2500N
                                 4" Aggregate Cap       2700N between 700E and 800E
                                 Dirt Shoulders            3070N between 700E and 800E
                                                                     700E between 2700N and 3070N


Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.