The following roads will be closed and reopened on 06/15/24:
- 2750N (from CH5 to 800E) seal coat
- 700E (from 2700N to 2750N) seal coat
- 900E (from 2600N to 2750N) seal coat
The following roads will be closed and reopened on 06/16/24:
- 2700N (from 700E to 800E) soil cement cure
The following roads will be closed and reopened on 06/21/24:
- 800E (from 2500N to 2750N) soil cement cure
In addition, the following work is anticipated for Monday 06/17/24 and Tuesday 06/18/24:
Monday 06/17/24: Culvert Installation: 2150N between CH 5 and 675E (C-245A)
Cement Stabilization: 2500N between 800E and 900E
Pre Pulverization: 2500N between 700E and 800E
Paint Pavt Mkr.: CH 5 between IL Rt 10 and County Line
4" Aggregate Cap: 2750N between 700E and 1000E
Dirt Shoulders: 3070N between 700E and 800E
700E between 2700N and 3070N
Tuesday 06/18/24: Culvert Installation: 2150N between CH 5 and 675E (C-245B)
Cement Stabilization: 2500N between 700E and 800E
Pre Pulverization: 700E between 2400N and 2500N
4" Aggregate Cap 2700N between 700E and 800E
Dirt Shoulders 3070N between 700E and 800E
700E between 2700N and 3070N
Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.