The following roads will be closed and reopened at the end of the day:
- 2150N (from CH5 to 675E) C-245A
The following roads will be closed and roepened on 06/17/24:
- CH5 (from IL RT10 to County Line) Paint pavt mkr line (moving operation)
- 2750N (from 700E to 1000E) aggregate capping
The following roads will be closed and roepened on 06/22/24:
- 800E (from 2600N to 2750N) soil cement cure
The following roads will be closed and roepened on 06/24/24:
- 800E (from 2600N to 2750N) soil cement stabilization
- 3070N (from 700E to 800E) dirt shoulders
- 700E (from 2700N to 3070N) dirt shoulder
The following roads will be closed and reopened on 06/25/24:
- 2500N (from 800E to 900E) soil cement stabilization
- 2500N (from 700E to 800E) pre-pulverization
In addition, the following work is anticipated for Tuesday 06/18/24:
Tuesday 06/18/24: Culvert Installation: 2150N between CH 5 and 675E (C-245B)
Cement Stabilization: 2500N between 700E and 800E
Pre Pulverization: 700E between 2400N and 2500N
4" Aggregate Cap 2700N between 700E and 800E
Dirt Shoulders 3070N between 700E and 800E
700E between 2700N and 3070N
Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.