Plan Of The Day: June 18

The following will be closed and reopened at end of day June 18 2024

  • 2150N (from CH 5 to 675E) Culvert 245B
  • 800E (from 2500N to 2600N) Pre-pulverization. Residents will have access to the north
  • 2750N (700E to 900E) Aggregate Capping.  Residents will have access to the east
  • 700E (from 2900N to 30370N) Dirt Shoulders.  Residents will have access to the north
  • 3070N (from 700E to 800E) Dirt Shoulders.  Residents will have access to east
  • 2750N (from CH 5 to 800E) Dirt Shoulders.  Residents will have access to the east
  • 800 E (from 2500N to 2750N) Soil Cement Cure.  Residents will have access to the north

The following will be closed 6/18/2024 and reopened 6/23/2024

  • 2500N (from 800E to 900E) Soil Cement Stabilization