Plan of the Day: June 19

The following roads will be closed and reopened at the end of the day:

  • 700E (from 2400N to 2500N) C-284
  • 2150N (from CH5 to 800E) pre-pulverization
  • 2700N (from 700E to 800E) aggregate capping
  • 2750N (from CH5 to 1000E) dirt shoulders
  • 2500N (from 800E to 900E) soil cement cure

The following roads will be closed and reopened on 06/21/24:

  • 800E (from 2500N to 2600N) soil cement cure

The following roads will be closed and reopened on 06/26/24:

  • 2500N (from 700E to 900E) soil cement stabilization

 


In addition, the following work is anticipated for Thursday 06/20/24/and Friday 06/21/24:

Thursday 06/20/24     Culvert Installation      3200N between 900E and 1000E (C-283)
                                   Cement Stabilization   2500N between 700E and 900E
                                   Pre Pu;lverization        2150N between CH 5 and 800E
                                   4" Aggregate Cap         800E between 2600N and 2750N
                                   Dirt Shoulders              2750N between CH 5 and 1000E

Friday    06/21/24      Culvert Installation       2150N between 700E and 775E
                                  Cement Stabilization    2150N between CH 5 and 600E
                                  Pre Pulverization          2150N between CH 5 and 800E
                                  4" Aggregate Cap         800E between 2500N and 2750N
                                  Dirt Shoulders               2750N between CH 5 and 1000E


   Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.