Following roads will be closed and reopened at the end of the day:
- 3200N (from 900E to 1000E) C-283
- 2150N (from CH5 to 800E) pre-pulverization
- 800E (from 2600N to 2750N) aggregate capping
- 2750N (from CH5 to 1000E) dirt shoulders
Following roads will be closed and reopened on 06/21/24:
- 800E (from 2500N to 2600N) soil cement cure
Following roads will be closed and reopened on 06/24/24:
- 2500N (from 700E to 900E) soil cement cure
Following roads will be closed an reopened on 06/26/24:
- 2500N (from 700E to 800E) soil cement stabilization
- 700E (from 2400N to 2500N) soil cement stabilization
In addition, the following work is anticipated for Friday 06/21/24:
Friday 06/21/24 Culvert Installation 2150N between 700E and 775E
Cement Stabilization 2150N between CH 5 and 600E
Pre Pulverization 2150N between CH 5 and 800E
4" Aggregate Cap 800E between 2500N and 2750N
Dirt Shoulders 2750N between CH 5 and 1000E
Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.