Plan of the Day: June 22

Following roads will be closed and reopened at the end of the day:

  • 2750N (from CH5 to 1000E) seal coat
  • 2700N (from 700E to 800E) seal coat
  • 800E (from 2500N to 2750N) seal coat

Following roads will be closed and reopened on 06/24/24:

  • 700E (from 2400N to 2500N) soil cement cure
  • 2500N (from 700E to 800E) soil cement cure

In addition, the following work is anticipated for Monday 06/24/24 and Tuesday 06/25/24:

Monday 06/24/24:   Culvert Installation             700E between 2400N and 2500N (C-284)
                                Cement Stabilization        2150N between CH5 and 600E
                                Pre Pulverization               600E between 2150N and 3rd Street
                                Dust Control (Seal Coat)  2750N between CH 5 and 1000E
                                Dirt Shoulders                    800E between 2500N and 2750N
                                4" Aggregate Cap            2500N between 800E and 900E

Tuesday 06/25/24:  Culvert Installation            2150N between 700E and 775E (C-109)
                               Cement Stabilization        2150N between 600E and 700E
                               Pre Pulverization               800E between 2150N and IL Rt 10
                               Dirt Shoulders                   800E between 2500N and 2750N
                               4" Aggregate Cap             2500N between 700E and 800E

Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstance.