Plan of the Day: June 24 (Monday)

Following roads will be closed and reopened at the end of the day:

  • 700E (from 2400N to 2500N) C-284
  • 600E (from 2150N to 3rd st) pre-pulverization
  • 2500N (from 700E to 800E) aggregate capping
  • 2750N (from CH5 to 900E) seal coat

Followings roads will be partially closed and reopened at the end of the day:

  • 900E (from 2600N to 2750N) dirt shoulders

Following roads will be closed and reopened on 06/30/24:

  • 2150N (from CH5 to 600E) soil cement stabilization
  • 700E (from 2400N to 2500N) soil cement cure

In addition, the following work is anticipated for Tuesday 06/25/24:

Tuesday 06/25/24:  Culvert Installation            2150N between 700E and 775E (C-109)
                               Cement Stabilization        2150N between 600E and 700E
                               Pre Pulverization               800E between 2150N and IL Rt 10
                               Dirt Shoulders                   800E between 2500N and 2750N
                               4" Aggregate Cap             2500N between 700E and 800E

Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstance.