The following roads will be closed and reopened at the end of the day:
- 800E (from 2300N to 2400N) pre-pulverization
- 800E (from 2500N to 2600N) aggregate capping
- 2500N (from 700E to 900E) aggregate capping
The following roads will be partially closed and reopened at the end of the day:
- 2750N (from 700E to 800E) dirt shoulders
- 2700N (from 700E to 800E) dirt shoulders
The following roads will be closed and reopened on 06/27/24:
- 775E (from 2050N to 2150N) C-42
The following roads will be closed and reopened on 07/02/24:
- 2150N (from CH5 to 700E) soil cement cure
- 600E (from 2150N to 3rd st) soil cement cure
In addition, the following work is anticipated for Thursday 06/27/24 and Friday 06/28/24:
Thursday 06/27/28: Culvert Installation 3200N between 900E and 1000E
Cement Stabilization 800E between 2150N and IL Rt 10
Dirt Shoulders 2750N between 700E and 1000E
2700N between 700E and 800E
Friday 06/28/24: Cement Stabilization 775E between 2050N and 2150N
4" Aggregate Cap 700E between 2400N and 2500N
Dirt Shoulders 2700N between 700E and 800E
Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.