The following roads will be closed and reopened at the end of the day:
- 800E (from 2500N to 2600N) seal coat
- 2500N (from 700E to 900E) seal coat
- 700E (from substation to 2500N)
The following roads will be partially closed and reopened at the end of the day:
- 2700N (from 700E to 800E) dirt shoulders
- 800E (from 2500N to 2750N) dirt shoulders
The following roads will be closed and reopened on 07/03/24:
- 800E (from IL RT10 to 2400N) soil cement cure
In addition, the following work is anticipated for Monday 07/01/2024 and Tuesday 07/02/2024:
07/01/2024: Culvert Installation 775E between 2050N and 2150N (C-42)
Cement Stabilization 800E between 2200N and IL Rt 10
Pre Pulverization 2150N between 700E and 800E
700E between 2300N and 2400N
4" Aggregate Cap 2150N between CH 5 and 600E
600E between 2150N and 3rd St.
07/02/2024: Culvert Installation 2150N between CH 5 and 600E (C-244B)
Cement Stabilization 775 E between 2050N and 2150N
Pre Pulverization 770 E between 2150N and 2300N
2400N between CH 5 and 700E
4" Aggregate Cap 2150N between 600E and 800E
Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.