Following roads will be closed for roadwork preparation for 03/02/24:
CH5 (from 2500N to 2700N),
1400E (from 3100N to 3300N),
900E (from I-74 to 3300N),
3200N (from 900E to 1100E),
1200E (from 3200N to 3400N),
2700N (from 700E to 800E),
900E (from 2600N to 2850N),
2750N (from CH5 to 700E),
Culvert work will take place along road closures on: CH5 (C-57,C-58),
Roads will be reopened at the end of the day.
Anticipated work schedule for 03/04/24 and 03/05/24:
03/04/24
Culvert installation
CH 5 (from 2500 N to 2600 N)
2500 N (from 800 E to 900 E)
1500 E (from 3200 N to 3300 N)
Roadway Prep.
2750N (from 1100 E to CH 5)
700 E (from 2700 N to 3050 N)
03/05/24
Culvert installation
3300 N (from 1400 E to 1500 E)
2500 N (from 700 E to 800 E)
Roadway Prep.
900 E (from 2600 N to U.S. 150)
2700 N (from 700 E to 800E)
Anticipated work schedules are subject to change due to weather, equipment breakdowns or any other unforeseen circumstance.