Plan of the Day: March 04

Following roads will be closed for roadwork preparation for 03/04/24:

1500E (from 3200N to 3300N) with Culvert work: C-1, 
CH5 (from 2500N to 2600N) with Culvert work: C-58, C-59,
700E (from 2700N to 3050N),
900E (from 2600N to US150),
800E (from 2700N to 2750N),
3200N (from 900E to 1100E),
1200E (from 3200N to 3300N),
900E (from I-74 to 3200N),
1200E (from 3300N to 3400N),

Roads will be reopened at the end of the day. 

** Click map to enlarge **

Anticipated work schedule for 03/05/24 and 03/06/24
               

Roadway Prep:         
900 E (from 2600 N to U.S. 150)
2700 N (from 700 E to 800E)

Culvert installation:   
3300 N (from 1400 E to 1500 E)
2500 N (from 700 E to 800 E)


Anticipated work schedules are subject to change due to weather, equipment breakdowns or any other unforeseen circumstance.