Plan of the Day: March 05

Following roads will be closed for roadwork preparation for 03/05/24:

CH5 (from 2400N to 2600N) with Culvert work: C-59, C-101,
3300N (from 1400E to 1500E) with Culvert work: C-3, 
1200E (from 3200N to 3400N),
900E (from US150 to 3400N),
2700N (from 700E to 800E),
800E (from 2700N to 2750N),
900E (from 2600N to US150),
2750N (from CH5 to 1000E),
3200N (from 1100E to 1200E)

Roads will be reopened at the end of the day. 

 

 

Anticipated work schedule for 03/06/24
               

Roadway Prep:         
900 E (from 2600 N to U.S. 150)
2700 N (from 700 E to 800E)

Culvert installation:   
3300 N (from 1400 E to 1500 E)
2500 N (from 700 E to 800 E)


Anticipated work schedules are subject to change due to weather, equipment breakdowns or any other unforeseen circumstance.