Following roads will be closed for roadwork preparation for 03/06/24:
2400N (from 400E to CH5) with Culvert work: C-101,
2500N (from 800E to 900E) with Culvert work: C-111,
1500E (from 3200N to 3300N) with Tile repair at C-1,
900E (from US150 to 3200N),
700E (from 2700N to 3050N),
2700N (from 725E to 800N),
900E (from 2600N to US150),
800E (from 2500N to 2750N),
Roads will be reopened at the end of the day.
In addition, the following work is anticipated for Thursday 03/07/24 and Friday 03/08/24:
03/07/24:
Roadway Prep.:
700 E between 2700 N and 3050 N
900 E between 2600 N and US 150
800 E between 2500 N and 2750 N
Culvert Install.:
2500N between 700E and 900E: C-111 & C-102 -
3300N between 1400 E and 1500E: C-4-
03/08/24:
Roadway Prep.:
900E between 2600N and US150
700E between 2700N and 3050N
800E between 2500N and 2750N
2750N between CH5 and 1000E
800E between 700E and 900E
Culvert Install:
2500N between 700E and 800E: C-102
700E between 2400N and 2500N: C-103
3300N between 1400E and 1500E: Riprap @ C-4
Anticipated work can be altered by weather, equipment breakdown or any other unforeseen circumstance.